Blue Line riders on Chicago’s West Side and in the western suburbs could see faster, more reliable trips after the next phase of a major track rebuild.
The Chicago Transit Board approved an $86.3 million design-build contract with Kiewit Infrastructure Company for track improvements between Kedzie and Pulaski on the Blue Line’s Forest Park Branch.
The project is expected to remove approximately 8,000 feet of slow zones, including the Pulaski Crossover. Construction is anticipated to begin in summer 2027 and last about 10 weeks, though the CTA has not outlined service arrangements for that period in its announcement.
What’s being rebuilt?
Crews will replace the tracks and underlying infrastructure between Kedzie and Pulaski, including the layers of material beneath the tracks, ties, and rails. The work also includes drainage improvements and upgrades to traction power, electrical, communications, and signal systems.
The goal is to restore operating speeds and improve reliability on a branch where, according to the CTA, about 84 percent is currently classified as a slow zone. Those restrictions require trains to run at reduced speeds for safety. Much of the branch’s infrastructure dates to 1958.
The CTA has not provided an estimate of how many minutes riders could save once this phase is complete.
Part of a bigger Blue Line overhaul
The Kedzie-to-Pulaski work is Phase 2 of the Forest Park Branch Rebuild Project, a multiyear effort to reconstruct the entire branch and make it fully accessible to people who use mobility devices. That accessibility goal applies to the broader rebuild—not just this track contract.
The first phase began in 2023 and included track and drainage work between UIC-Halsted and Illinois Medical District, along with reconstructing Racine station to make it ADA-accessible.
The broader corridor effort is coordinated through the Connect 290 Blue Program, which brings together the CTA, the Illinois Department of Transportation, and the Chicago Metropolitan Agency for Planning. Federal Reconnecting Communities Program funding is helping support the Kedzie-to-Pulaski project.
What riders should expect
Construction is currently expected to start in summer 2027 and last about 10 weeks. The CTA’s announcement does not specify whether riders should expect station closures, shuttle buses, or other service changes during the work.
For now, riders should watch for future CTA announcements and service alerts as construction approaches.